Energia Yuga continues the construction of two substations for the Novolakskaya Wind Power Plant

The creation of the Caspian Wind Cluster is underway in Dagestan. At the junction of the Novolaksky, Babayurtovsky, and Kizlyarsky districts of the republic, Rosatom Renewable Energy is constructing the Novolakskaya Wind Power Plant. The total capacity of the wind turbines is expected to reach 300 megawatts. In 2025, 61 wind turbines will be installed, and in 2026, another 59 will be added.

Energia Yuga continues constructing two substations for the new wind farm. At switchgear-1, the installation of the wind farm's auxiliary service building (ASB); the 35 kV indoor switchgear (ISG), the 110 kV prefabricated transformer substation (PTS), and the checkpoint has been completed. Two TDN-80000/110 power transformers, lighting masts, 110 kV portals, 35 kV switchgear (GIS) equipment, as well as relay protection and automation (RPA) and fiber-optic communication systems (FOCS) have been installed.

At switchgear -2, the installation of the wind farm's auxiliary service building (ASB), combined with the 35 kV indoor switchgear (ISG), and the 35 kV switchgear (GIS) celles is currently in progress.

Completion of construction