Construction of a substation 330 kV for AO «NovaWind»
2020
Stavropol Territory
The substation 330 kV «Barsuki» was constructed by our company for Kochubeevskaya wind power station.
AO «NovaWind» wind park in the Stavropol Territory has 210 MW of total capacity, 84 wind turbines, 200 hectares of total area; it is a project that can take the entire renewable energy sector in Russia to a new level. As per contract, «Energia Yuga» company has completed development of working documentation, construction, start-up and adjustment operations of the 330 kV substation «Barsuki» with installation of two transformers with capacity of 125 MVA each and construction of a 330 kV double-circuit overhead power line from Nevinnomyssk to Barsuki. Project Manager: Stanislav Pichugin.