Construction of a substation 220/35/6 kV for the Ilsky oil refinery
2022
Krasnodar region
A new substation provided reliable power supply to existing facilities and a resource for expanding production capacities.
In the Seversky district of the Krasnodar region «Energia Yuga» company has built a 220/35/6 kV Ilskaya substation with incoming 220 kV overhead line Kubanskaya -Ilskaya and incoming 220 kV overhead line Afipskaya-Ilskaya. The substation is equipped with two power transformers (each with a capacity of 63 MVA), twelve 35 kV outdoor switchgear cells and 58 6 kV indoor switchgear cells installed at the facility. Project Manager – Alexander Grembovsky.