Energia Yuga is beginning work on a new project, the Verbnaya wind farm, in the Rostov region
Energia Yuga continues its cooperation with Rosatom Renewable Energy JSC. The division of the State Atomic Energy Corporation responsible for the implementation of the Wind Energy Strategy will build the Verbnaya wind power plant the Rostov Region.

 Our specialists will revise design documentation, develop working documentation, and provide supervision for the implementation of the Verbnaya Wind Farm project. The scope of the design includes the sites and foundations of the wind turbines, 37 complete transformer substations 35/0.69 kV, on-site cable networks (35 kV cable lines, fiber-optic communication lines) with a total length of about 36 km, the Verbnaya substation 35/110 kV, which includes a 110 kV outdoor switchgear, a 35 kV indoor switchgear combined with a substation control building and two 62.9 MVA power transformers. Sergey Leonov has been appointed project manager.

Photo by Rosatom Renewable Energy JSC.