The reconstruction of the substation will be carried out in three technological stages. In the first stage, we will install a new general substation control building, complete outdoor switchgear 10 kV, an arc extinguishing reactor, a station servis transformer, a three-phase double-winding oil Immersed transformer 110/35/10 kV , and replace the portals, busbars, and some of the equipment in the 35 kV outdoor switchgear and the 110 kV outdoor switchgear. Next, we will install a second transformer, upgrade the rest of the substation equipment, and complete all necessary commissioning activities in the final stage.
The project will allow new consumers on the Taman Peninsula to be connected to the power grid, and it will also open up opportunities for the socio-economic development of the Temryuk district.